AL-YAMAMA
ENGINEERING CO.
Project Details:
Description of work: Early Works (Phase 2) Site Preparation for Basrah NGL Project
Location: ROO
Contract Starting Date:01/02/2019
Contract Expiry Date:20/06/2019
Description of work: NV33691 (SIGUP-148) BGC Building upgrades
Location: BGC
Contract Starting Date:13/12/2013
Contract Expiry Date:12/08/2015
Description of work: UI-43199 Umm Qsar Marine Terminal –Civil Works Project
Location: BGC
Contract Starting Date:21/11/2013
Contract Expiry Date:31/07/2015
Description of work: Basrah Gas Company Temporary Office at KAZ and Rumaila - Teleconference
Location: BGC
Contract Starting Date:01/04/2013
Contract Expiry Date:30/03/2015
Description of work: Contract#UI42859 for OFF POLT at NR IBC CIVILS WORKS
Location: MOF
Contract Starting Date:15/04/2014
Contract Expiry Date:15/03/2015
Description of work: Hammar Mishrif Civil Works SIGUP-12-082
Location: BGC
Contract Starting Date:01/05/2013
Contract Expiry Date:30/09/2014
Description of work: North Rumaila Inlet Booster Compressor Station- Civil Work
Location: BGC
Contract Starting Date:08/08/2012
Contract Expiry Date:31/07/2014
Description of work: UI37964 - ISI Contract Interim Security Improvement for BGC NR NGL, UQ Storage and Marine Terminals
Location: BGC
Contract Starting Date:21/11/2013
Contract Expiry Date:21/01/2014